MoDOT, District 8, Springfield -- Drivers can expect one-lane traffic and delays on Greene County Route MM through Brookline the rest of the week.
A resurfacing project is scheduled to begin on Wednesday, May 18, the Missouri Department of Transportation said.
A contractor crew has ground off sections of old pavement between Route 60/413 east of Republic and I-44 north of Brookline and will resurface the highway.
Drivers can expect one-lane traffic where the paving crew is working.
Crews will be working on the roadway from roughly 7 a.m. to 5 p.m. Monday through Friday.
Flaggers will direct drivers through the work zone.
Drivers are urged to slow down when approaching the project and be prepared to stop.
The entire 2.6-mile length of Route MM will receive a new 1-3/4 inch driving surface.
The prime contractor on the project is APAC-Missouri of Columbia for a low bid amount of $170,206.