The Safe & Sound Bridge Program in Northwest Missouri will improve 190 bridges by December 31, 2013. Some of these bridges will be completely replaced with new structures, while others will receive new bridge decks and possible improvements to other bridge structural components.
Please note that all dates listed below for upcoming bridge construction and closures are tentative and subject to change.
|

Now Closed:
ATCHISON COUNTY
MO 46 - HICKORY CREEK
US 136 - COW CREEK
BUCHANAN COUNTY
MO 116 - LITTLE BEE CREEK
CALDWELL COUNTY
ROUTE D - GOOSE CREEK
US 36 HWY. (Westbound) UPRR Bridge
ROUTE W - EAST SHEEP CREEK
CLINTON COUNTY
Route NN - MCGUIRE CREEK
DAVIESS COUNTY
ROUTE E - GRINDSTONE CREEK
DEKALB COUNTY
ROUTE E - LOST CREEK
NODAWAY COUNTY
ROUTE VV - LONG BRANCH
|
|
PROJECT COMPLETE
 
Before After
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 59 Hwy. / Bus. 71 Hwy. (northbound)
Bridge location: at Interstate 29
Work to be done: Bridge redeck
Originally built: 1962
Awarded on: May 11, 2010
Award amount: $1,816.999.30 (Includes work on north & southbound bridges)
Awarded to: Loch Sand & Construction, Co.
Construction begins: June 14, 2010
Closure date: July 21, 2010
Construction complete: November 2, 2010
Route: U.S. 59 Hwy. / Bus. 71 Hwy. (southbound)
Bridge location: at Interstate 29
Work to be done: Bridge redeck
Originally built: 1962
Awarded on: May 11, 2010
Award amount: $1,816.999.30 (Includes work on north & southbound bridges)
Awarded to: Loch Sand & Construction, Co.
Construction begins: June 14, 2010
Closure date: September 8, 2010
Construction complete: November 2, 2010
|
| |
|
|

|
|
Route: U.S. 169 Hwy.
Bridge location: Niagara Creek at Rochester
Work to be done: Bridge replacement
Originally built: 1928
Awarded to: KTU Constructors (Design-Build Contract)
Scheduled for construction: July 9, 2012
Detour map: Click here for U.S. 169 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 48
Bridge location: MO 48 at Platte River Overflow
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 16, 2011
Construction completed: June 22, 2011 (Closed 37 days) Detour map: Click here for MO 48 Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route H
Bridge location: Pedlar Creek
Work to be done: Bridge redeck
Originally built: 1954
Awarded on: December 5, 2008
Award amount: $208,455.90
Awarded to: Boone Construction Company
Closure date: April 6, 2009
Construction completed: May 20, 2009 (Closed 44 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route DD
Bridge location: Dillon Creek
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 21, 2010
Construction completed: August 24, 2010 (Closed 65 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route Y
Bridge location: Owl Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 16, 2011
Construction completed: June 28, 2011 (Closed 44 days) Detour map: Click here for Route Y Detour
|
| |
|
|
PROJECT COMPLETE

Before After
|
|
Route: Route H
Bridge location: Arapahoe Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 7, 2010
Construction completed: October 28, 2010 (Closed 51 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route A
Bridge location: drainage ditch
Work to be done: Bridge replacement
Originally built: 1930
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 6, 2011
Construction completed: August 15, 2011 (Closed 39 days)
Detour map: Click here for Route A Detour
|
PROJECT COMPLETE

Before |
|
Route: U.S. 59 Hwy.
Bridge location: at Tarkio River
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: January 30, 2012 Construction completed: April 16, 2012 (Closed 77 days ) Detour Map: Click here for U.S. 59 Hwy. Detour
|
| |
|
|
NOW CLOSED

|
|
Route: U.S. 136 Hwy.
Bridge location: Cow Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 21, 2012 (Six to eight week closure) Detour Map:Click here for US 136 Hwy. Detour
|
NOW CLOSED

|
|
Route: MO 46
Bridge location: Hickory Creek
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 14, 2012 (Six to eight week closure)
Detour Map: Click here for MO 46 Detour |
| |
|
|
 |
|
Route: U.S. 136 Hwy.
Bridge location: Little Tarkio Creek
Work to be done: Bridge replacement
Originally built: 1931
Project letting: April 20, 2012
Scheduled for construction: 2012
Detour Map: Click here for U.S. 136 Hwy. Detour
This bridge is on the Statewide Transportation Improvement Program (STIP)
and is not a part of the Safe & Sound program. |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 46
Bridge location: Little Tarkio Drainage Ditch
Work to be done: Bridge replacement
Originally built: 1935
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: June 3, 2011
Construction completed: August 11, 2011 (Closed 65 days)
Detour Map: Click here for MO 46 Detour |
| |
|
|
PROJECT COMPLETE  
Before After |
|
Route: U.S. 275 Hwy.
Bridge location: Kings Bridge
Work to be done: Bridge redeck
Originally built: 1951
Awarded on: March 4th
Award amount: $255,037.80
Awarded to: A.M. Cohron & Sons, Inc.
Closure date: June 1, 2009
Construction completed: July 27, 2009 (Closed 53 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Mid Tarkio Creek
Work to be done: Bridge replacement
Originally built: 1938
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 31, 2011
Construction completed: August 3, 2011 (Closed 63 days)
Detour Map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route C
Bridge location: Tarkio River
Work to be done: Bridge replacement
Originally built: 1938
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 4, 2011
Construction completed: October 18, 2011 (Closed 74 days)
Detour Map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Long Branch Creek
Work to be done: Bridge redeck
Originally built: 1961
Awarded on: March 4th
Award Amount: $216,274.78
Awarded to: A.M. Cohron & Sons, Inc.
Closure Date: April 7, 2009
Construction completed: May 28, 2009 (Closed 50 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route V
Bridge location: Main Drainage Ditch #6
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 14, 2011
Construction completed: May 23, 2011 (Closed 71 days)
Detour Map: Click here for Route V Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route B
Bridge location: Halls Branch
Work to be done: Bridge replacement
Originally built: 1930
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 3, 2011
Construction completed: June 17, 2011 (Closed 46 days)
Detour Map: Click here for Route B Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 46
Bridge location: East Fork Hickory Creek
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 15, 2011
Construction completed: September 14, 2011 (Closed 29 days)
Detour Map: Click here for MO 46 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 111
Bridge location: Turkey Creek
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: November 7, 2011
Construction completed: December 9, 2011 (Closed 32 days)
Detour Map: Click here for MO 111 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 111
Bridge location: Drainage Ditch
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: October 31, 2011
Construction completed: December 9, 2011 (Closed 39 days)
Detour Map: Click here for MO 111 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route B
Bridge location: Rock Creek
Work to be done: Bridge replacement
Originally built: 1948
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 12, 2011
Construction completed: October 25, 2011 (Closed 43 days)
Detour Map: Click here for Route B Detour
|
PROJECT COMPLETE
 
Before After |
|
Route: Route O
Bridge location: Interstate 29
Work to be done: Bridge redeck
Originally built: 1958
Community briefing held: Tuesday, February 24, 2009
Awarded on: April 1, 2009
Award amount: $401,870.00
Awarded to: Clarkson Construction Company
Closure date: September 8, 2009
Construction completed: October 9, 2009 (Closed 30 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: U.S. 169 Hwy.
Bridge location: Interstate 29
Work to be done: Bridge redeck
Originally built: 1962
Community briefing held: Thursday, February 26, 2009
Awarded on: April 1, 2009
Award amount: $1,067,858.00
Awarded to: Clarkson Construction Company
Closure date: July 10, 2009
Construction completed: August 25, 2009 (Closed 48 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route CC
Bridge location: South Fork of Bee Creek
Work to be done: Bridge redeck
Originally built: 1969
Community briefing held: Tuesday, February 24, 2009
Awarded on: April 1, 2009
Award amount: $326,088.40
Awarded to: Clarkson Construction Company
Closure date: June 8, 2009
Construction completed: July 18, 2009 (Closed 41 days) |
| |
|
|
PROJECT COMPLETE

Before |
|
Route: U.S. 59 Hwy.
Bridge location: Cloverdale Ditch
Work to be done: Bridge replacement
Originally built: 1941
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 19, 2012
Construction completed: May 3, 2012 (Closed 45 days)
Detour Map: Click here for US 59 Hwy. Detour |
| |
|
|
PROJECT COMPLETE

Before |
|
Route: U.S. 59 Hwy.
Bridge location: Gay Branch
Work to be done: Bridge replacement
Originally built: 1920
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 19, 2012
Construction completed: May 3, 2012 (Closed 45 days)
Detour Map: Click here for US 59 Hwy. Detour
|
| |
|
|
 |
|
Route: MO 116
Bridge location: Lost Creek
Work to be done: Bridge replacement
Originally built: 1950
Awarded to: KTU Constructors (Design-Build Contract)
Scheduled for construction: June 18, 2012
Detour Map: Click here for MO 116 Detour
|
| |
|
|
 |
|
Route: Route M
Bridge location: Sugar Creek
Work to be done: Bridge replacement
Originally built: 1956
Awarded to: KTU Constructors (Design-Build Contract)
Scheduled for construction: June 25, 2012
Detour Map: Click here for Route M Detour
|
| |
|
|
 |
|
Route: Route DD
Bridge location: Malden Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Scheduled for construction: July 23, 2012
Detour Map: Click here for Route DD Detour
|
| |
|
|
PROJECT COMPLETE

Before |
|
Route: MO 116
Bridge location: Bee Creek
Work to be done: Bridge replacement
Originally built: 1933
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 19, 2012
Construction completed: April 26, 2012 (Closed 38 days)
Detour Map: Click here for MO 116 Detour
|
| |
|
|
NOW CLOSED

|
|
Route: MO 116
Bridge location: Little Bee Creek
Work to be done: Bridge replacement
Originally built: 1933
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 14, 2012 (Six to eight week closure)
Detour Map: Click here for MO 116 Detour
|
| |
|
|
PROJECT COMPLETE

Before |
|
Route: Route P
Bridge location: Third Fork of Platte River
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: March 12, 2012
Construction completed: April 26, 2012 (Closed 44 days)
Detour Map: Click here for Route P Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route KK
Bridge location: Puckett Slu
Work to be done: Bridge replacement
Originally built: 1936
Awarded on: May, 2009
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 19, 2009
Construction completed: November 10, 2009 (Closed 22 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route H
Bridge location: Wolfpen Creek
Work to be done: Bridge replacement
Originally built: 1948
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 3, 2011
Construction completed: November 3, 2011 (Closed 30 days)
Detour Map: Click here for Route H Detour |
| |
|
|
NOW CLOSED

|
|
Route: US 36 Hwy. (westbound)
Bridge location: Union Pacific Railroad Bridge
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: April 30, 2012 (Six to eight week closure) Detour map: Click here for U.S. 36 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 116
Bridge location: N. Mud Creek
Work to be done: Bridge redeck
Originally built: 1964
Awarded on: September 2, 2009
Award amount: $267,963.00
Awarded to: Chester Bross Cons. Co./C.B. Equipment, Inc.
Closure date: April 5, 2010
Completed: May 20th 2010 (Closed 45 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route A
Bridge location: Dead Oak Creek
Work to be done: Bridge redeck
Originally built: 1966 Awarded on: September 2, 2009
Award amount: $177,808.50
Awarded to: Chester Bross Cons. Co./C.B. Equipment, Inc.
Closure date: May 24, 2010
Completed: June 23, 2010 (Closed 29 days) |
| |
|
|
NOW CLOSED

Before |
|
Route: Route W
Bridge location: East Sheep Creek
Work to be done: Bridge replacement
Originally built: 1923
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 7, 2012 (Six to eight week closure)
Detour map: Click here for Route W Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route N
Bridge location: Mud Creek
Work to be done: Bridge redeck
Originally built: 1958 Awarded on: September 2, 2009
Award amount: $236,095.00
Awarded to: Chester Bross Cons. Co./C.B. Equipment, Inc.
Closure date: April 19, 2010
Construction completed: June 4, 2010 (Closed 47 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route U
Bridge location: Otter Creek
Work to be done: Bridge redeck
Originally built: 1960
Awarded to: Widel Inc.
Closure date: April 25, 2011
Construction completed: June 29, 2011 (Closed 65 days)
Detour map: Click here for Route U Detour
|
| |
|
|
NOW CLOSED

Before |
|
Route: Route D
Bridge location: Goose Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract) Closure date: April 23, 2012 (Six to eight week closure)
Detour map: Click here for Route D Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route HH
Bridge location: Plum Creek
Work to be done: Bridge redeck
Originally built: 1965
Awarded to: Widel Inc.
Closure date: June 1, 2011
Construction completed: July 15, 2011 (Closed 44 days)
Detour map: Click here for Route HH Detour
|
| |
|
|
PROJECT COMPLETE

Before |
|
Route: Route A
Bridge location: Panther Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 2, 2012
Construction completed: May 10, 2012 (Closed 39 days)
Detour map: Click here for Route A Detour
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route E
Bridge location: Fish Pond Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract) Closure date: June 25, 2010
Construction completed: July 24, 2010 (Closed 37 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route E
Bridge location: McCroskie Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract) Closure date: April 25, 2010
Construction completed: July 3, 2010 (Closed 84 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route B
Bridge location: Camp Creek
Work to be done: Bridge replacement
Originally built: 1951
Awarded to: KTU Constructors (Design-Build Contract) Closure date: April 25, 2010
Construction completed: May 24, 2010 (Closed 36 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route B
Bridge location: Camp Creek
Work to be done: Bridge replacement
Originally built: 1930
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 19, 2010
Construction completed: June 30, 2010 (Closed 35 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route OO
Bridge location: McCroskie Creek
Work to be done: Bridge replacement
Originally built: 1956
Awarded to: KTU Constructors (Design-Build Contract) Closure date: July 19, 2010
Construction completed: August 27, 2010 (Closed 37 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Big Creek
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 28, 2010
Construction completed: August 20, 2010 (Closed 53 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Bridge Creek
Work to be done: Bridge deck replacement
Originally built: 1958
Awarded to: Widel, Inc.
Closure date: September 2, 2009
Construction completed: October 30, 2009 (Closed 59 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Wolf Creek
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract) Closure date: April 4, 2011
Construction completed: May 3, 2011 (Closed 36 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route W
Bridge location: Burr Oak Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract) Closure date: May 14, 2011
Construction completed: July 1, 2010 (Closed 46 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 139
Bridge location: Big Creek Overflow
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 18, 2010
Construction completed: November 24, 2010 (Closed 114 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route 139
Bridge location: Big Creek Drainage Ditch
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract) Closure date: August 18, 2010
Construction completed: November 24, 2010 (Closed 114 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route 139
Bridge location: Big Creek
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract) Closure date: August 18, 2010
Construction completed: November 24, 2010 (Closed 114 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route J
Bridge location: Mound Creek
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract) Closure date: April 12, 2010
Construction completed: May 21, 2010 (Closed 43 days) |

|
|
Route: MO 11
Bridge location: BNSF
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract) Closure date: July 9, 2012
Detour map: Click here for MO 11 Detour
|
PROJECT COMPLETE
 
Before After |
|
Route: Route P
Bridge location: Puzzle Creek
Work to be done: Bridge replacement
Originally built: 1948
Awarded to: KTU Constructors (Design-Build Contract) Closure date: March 7, 2011
Construction completed: April 14, 2011 (Closed 53 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route PP
Bridge location: New Hope Creek
Work to be done: Bridge replacement
Originally built: 1959
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 12, 2011 Construction completed: October 18, 2011 (Closed 36 days) Detour Map: Click here for Route PP Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route K
Bridge location: Castile Creek
Work to be done: Bridge redeck
Originally built: 1960
Awarded to: Widel Inc.
Closure date: February 28, 2011
Construction complete: April 29, 2011 (Closed 59 days)
Detour Map: Click here for Route K Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route V
Bridge location: Interstate 35
Work to be done: Bridge redeck
Originally built: 1964
Awarded to: Widel Inc.
Closure date: March 14, 2011
Construction complete: May 6, 2011 (Closed 52 days)
Detour Map: Click here for Route V Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 121
Bridge location: Deer Creek
Work to be done: Bridge replacement
Originally built: 1935
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 10, 2011
Construction complete: November 10, 2011 (Closed 30 days)
Detour Map: Click here for MO 121 Detour |
| |
|
|
NOW CLOSED

Before |
|
Route: Route NN
Bridge location: McGuire Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 7, 2012 (Six to eight week closure)
Detour Map: Click here for Route NN Detour |
PROJECT COMPLETE
 
Before After |
|
Route: Route RA
Bridge location: East Brushy Creek
Work to be done: Bridge redeck
Originally built: 1972
Awarded on: January 8, 2009
Award amount: $299,419.00
Awarded to: Chester Bross Construction Company
Closure date: May 26, 2009
Construction completed: June 30, 2009 (Closed 35 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 13
Bridge location: Little Cypress Creek
Work to be done: Bridge replacement
Originally built: 1937
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: October 31, 2011
Construction completed: December 13, 2011 (Closed 43 days)
Detour Map: Click here for MO 13 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route T
Bridge location: Sampson Creek
Work to be done: Bridge redeck
Originally built: 1957
Awarded to: Comanche Construction Inc.
Award amount: $750,543.90
Closure date: March 7, 2011
Construction completed: April 27, 2011 (Closed 50 days)
|
| |
|
|
PROJECT COMPLETE

Before |
|
Route: Route CC
Bridge location: Dog Creek
Work to be done: Bridge bridge replacement
Originally built: 1953
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 12, 2012
Construction completed: April 24, 2012 (Closed 44 days)
Detour Map: Click here for Route CC Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route P
Bridge location: Pilot Grove Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 28, 2011
Construction completed: May 10, 2011 (Closed 42 days)
Detour Map: Click here for Route P Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route P
Bridge location: Big Muddy Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 6, 2011
Construction completed: October 14, 2011 (Closed 38 days)
Detour Map: Click here for Route P Detour
|
| |
|
|
NOW CLOSED

Before |
|
Route: Route E
Bridge location: Grindstone Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: April 2, 2012 (Six to eight week closure)
Detour Map: Click here for Route E Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route V
Bridge location: Muddy Creek
Work to be done: Bridge redeck
Originally built: 1963
Awarded to: Widel, Inc.
Closure date: July 12, 2011
Construction completed: September 6, 2011 (Closed 54 days)
Detour Map: Click here for Route V Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route Z
Bridge location: Drainage ditch
Work to be done: Bridge redeck
Originally built: 1961
Awarded to: Widel, Inc.
Closure date: June 28, 2011
Construction completed: August 23, 2011 (Closed 55 days)
Detour Map: Click here for Route Z Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route HH
Bridge location: Marrowbone Creek
Work to be done: Bridge redeck
Originally built: 1962
Awarded to: Widel, Inc.
Closure date: August 23, 2011
Construction completed: October 20, 2011 (Closed 57 days)
Detour Map: Click here for Route HH Detour
|
| |
|
|
 |
|
Route: Route J
Bridge location: Dog Creek
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Scheduled for construction: May 29, 2012
Detour Map: Click here for Route J Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route K
Bridge location: East Creek
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 16, 2011
Construction completed: June 9, 2011 (Closed 23 days)
Detour Map: Click here for Route K Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route K
Bridge location: Pilot Grove Creek
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 6, 2011
Construction completed: July 1, 2011 (Closed 25 days)
Detour Map: Click here for Route K Detour |
| |
|
|
 |
|
Route: Route J
Bridge location: Marrowbone Creek
Work to be done: Bridge replacement
Originally built: 1935
Awarded to: KTU Constructors (Design-Build Contract)
Scheduled for construction: June 18, 2012
Detour Map: Click here for Route J Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route M
Bridge location: Lick Fork Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: August 8, 2011
Construction completed: September 19, 2011 (Closed 41 days)
Detour Map: Click here for Route M Detour
|
PROJECT COMPLETE
 
Before After
|
|
Route: MO 33
Bridge location: Branch of Lost Creek (Red Horse Creek)
Work to be done: Bridge redeck
Originally built: 1959
Awarded on: December 2, 2009
Award amount: $258,526.93
Awarded to: Loch Sand & Construction Co.
Closure date: March 22, 2010
Construction completed: April 27, 2010 (Closed 36 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: MO 33
Bridge location: West Fork Lost Creek
Work to be done: Bridge redeck
Originally built: 1959
Awarded on: December 2, 2009
Award amount: $252,744.35
Awarded to: Loch Sand & Construction Co.
Closure date: April 27, 2010
Construction completed: June 3, 2010 (Closed 37 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 36 Hwy. (westbound)
Bridge location: Castile Creek
Work to be done: Bridge replacement
Originally built: 1923
Awarded to: KTU Constructors (Design-Build Contract) Closure date: May 4, 2011
Construction completed: June 16, 2011 (Closed 42 days)
Detour map: Click here for U.S. 36 Hwy. Westbound Detour |
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 36 Hwy. (eastbound)
Bridge location: Castile Creek
Work to be done: Bridge redeck
Originally built: 1966 Closed for construction: July 18, 2011
Construction completed: September 9, 2011 (Closed 51 days)
Detour map: Click here for U.S. 36 Hwy. Eastbound Detour
|
|
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 36 Hwy. (westbound)
Bridge location: Grindstone Creek
Work to be done: Bridge redeck
Originally built: 1966 Closed for construction: August 29, 2011
Construction completed: October 12, 2011 (Closed 43 days)
Detour map: Click here for U.S. 36 Hwy. Westbound Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route A
Bridge location: East Fork Lost Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract) Closed for construction: October 17, 2011
Construction completed: December 6, 2011 (Closed 49 days)
Detour map: Click here for Route A Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route E
Bridge location: North Fork Lost Creek
Work to be done: Bridge redeck
Originally built: 1956
Awarded on: January 8, 2009
Award amount: $227,405.00
Awarded to: St. Joseph Fuel Oil & Mfg. Co.
Closure date: June 22, 2009
Construction completed: August 6, 2009 (Closed 45 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route V
Bridge location: Third Fork Platte River
Work to be done: Bridge redeck
Originally built: 1957
Award amount: $277,330.00
Awarded to: St. Joseph Fuel Oil & Mfg. Co.
Closure date: March 30, 2009
Construction completed: May 14, 2009 (Closed 46 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route F
Bridge location: Crooked Creek
Work to be done: Bridge redeck
Originally built: 1961 Award amount: $291,606.84 Awarded to: Chester Bross Const. Co. / C.B. Equipment Inc. Closure date: August 29, 2011 Construction completed: October 21, 2011 (Closed 52 days)
Detour map: Click here for Route F Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Grindstone Creek
Work to be done: Bridge redeck
Originally built: 1952
Awarded on: January 8, 2009
Award amount: $271,372.00
Awarded to: St. Joseph Fuel Oil & Mfg. Co.
Closure date: May 11, 2009
Construction completed: June 25, 2009 (Closed 45 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route H
Bridge location: Dry Branch
Work to be done: Bridge replacement
Originally built: 1953
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 26, 2011
Construction completed: October 20, 2011
Detour map: Click here for Route H Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route J
Bridge location: Abandoned Railroad Bridge
Work to be done: Bridge removal
Originally built: 1964
Awarded on: May 11, 2010
Award amount: $178,145.79
Awarded to: Widel, Inc.
Closure date: August 2, 2010
Construction completed: September 14, 2010 (Closed 44 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route E
Bridge location: Little Third Fork Platte
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: November 7, 2011
Construction completed: December 14, 2011 (Closed 37 days)
Detour map: Click here for Route E Detour |
| |
|
|
NOW CLOSED

|
|
Route: Route E
Bridge location: Lost Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract) Closed for construction: May 14, 2012 (Six to eight week closure)
Detour map: Click here for Route E Detour |
| |
|
|
 |
|
Route: Route E
Bridge location: East Fork Lost Creek
Work to be done: Bridge replacement
Originally built: 1941
Awarded to: KTU Constructors (Design-Build Contract) Scheduled for construction: June 11, 2012 Detour map: Click here for Route E Detour
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 169 Hwy.
Bridge location: Old Channel Island Creek
Work to be done: Bridge removal
Originally built: 1941
Closure date: April 3, 2012
Construction completed: April 11, 2012 (Closed 9 days)
Detour Map: Click here for US 169 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 85
Bridge location: Thompson Branch
Work to be done: Bridge redeck
Originally built: 1925
Closure date: January 25, 2012
Construction completed: April 7, 2012 (Closed 73 days)
Detour Map: Click here for MO 85 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 85
Bridge location: Town Creek
Work to be done: Bridge replacement
Originally built: 1925
Awarded to: KTU Constructors (Design-Build Contract) Closure date: May 31, 2011
Construction completed: July 8, 2011 (Closed 37 days)
Detour Map: Click here for MO 85 Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 136 Hwy.
Bridge location: Town Branch
Work to be done: Bridge replacement
Originally built: 1929
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 6, 2011
Construction completed: July 20, 2011 (Closed 44 days) Detour Map: Click here for U.S. 136 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 136 Hwy.
Bridge location: Moccasin Creek
Work to be done: Bridge replacement
Originally built: 1929
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: August 15, 2011
Construction completed: October 3, 2011 (Closed 48 days)
Detour Map: Click here for U.S. 136 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route UU
Bridge location: Turkey Creek
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 7, 2010
Construction completed: October 30, 2010 (Closed 53 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route BB
Bridge location: Island Creek
Work to be done: Bridge redeck
Awarded on: January 9, 2009
Award amount: $230,416.00
Awarded to: Chester Bross Construction Company
Closure date: June 8, 2009
Construction completed: July 10, 2009 (Closed 33 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route O
Bridge location: West Fork Grand River
Work to be done: Bridge replacement
Originally built: 1960
Awarded to: KTU Constructors (Design-Build Contract) Closure date: February 9, 2011
Construction completed: May 11, 2011 (Closed 90 days)
Detour Map: Click here for Route O Detour |
| |
|
|
PROJECT COMPLETE  
Before After |
|
Route: Route A
Bridge location: Evona Creek
Work to be done: Bridge replacement
Originally built: 1930
Awarded to: KTU Constructors (Design-Build Contract) Closure date: October 11, 2010
Construction completed: November 11, 2010 (Closed 30 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route H
Bridge location: West Fork Grand River
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: August 15, 2011
Construction completed: October 12, 2011 (Closed 57 days)
Detour Map: Click here for Route H Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Island Creek
Work to be done: Bridge replacement
Originally built: 1948
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 14, 2011
Construction completed: May 4, 2011 (Closed 51 days)
Detour Map: Click here for Route M Detour
|
PROJECT COMPLETE
 
Before After |
|
Route: Route WW
Bridge location: Hickory Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 24, 2010
Construction completed: October 13, 2010 (Closed 47 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route E
Bridge location: Crooked Creek
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 13, 2010
Construction completed: October 5, 2010 (Closed 35 days) |
PROJECT COMPLETE
 
Before After
|
|
Route: U.S. 69 Hwy
Bridge location: Big Creek
Work to be done: Bridge replacement
Originally built: 1928
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 13, 2010
Construction completed: November 10, 2010 (Closed 57 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: U.S. 69 Hwy.
Bridge location: Big Creek Overflow
Work to be done: Bridge replacement
Originally built: 1928
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 4, 2010 Construction completed: November 10, 2010 (Closed 36 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 136 Hwy.
Bridge location: Sugar Creek
Work to be done: Bridge replacement
Originally built: 1937
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 18, 2011
Construction completed: August 17, 2011 (Closed 29 days)
Detour map: Click here for U.S. 136 Hwy. Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route MM
Bridge location: Fox Creek
Work to be done: Bridge redeck
Originally built: 1962
Award amount: $135,150.00
Awarded to: Chester Bross Construction Co.
Closure date: August 10, 2010
Construction completed: September 21, 2010 (Closed 42 days)
Detour map: Click here for Route MM Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Big Muddy Creek
Work to be done: Bridge redeck
Originally built: 1957
Award amount: $234,973.32
Awarded to: Loch Sand and Construction Co.
Closure Date: May 6, 2009
Construction completed: June 9, 2009 (Closed 34 days)
Bridge Painting Project: Scheduled For 2010
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route UU
Bridge location: Indian Creek
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: November 1, 2010
Construction completed: December 23, 2010 (Closed 52 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route KK
Bridge location: Shain Creek
Work to be done: Bridge replacement
Originally built: 1959
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 26, 2010
Construction completed: June 9, 2010 (Closed 44 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route HH
Bridge location: Lotts Creek
Work to be done: Bridge redeck
Originally built: 1960
Award amount: $268,942.92
Awarded to: Loch Sand and Construction Co.
Closure date: May 26, 2009
Construction completed: July 8, 2009 (Closed 43 days) Bridge Painting Project: Scheduled For 2010
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route MM
Bridge location: Sugar Creek
Work to be done: Bridge redeck
Originally built: 1962
Award amount: $174,338.00
Awarded to: Chester Bross Construction Co.
Closure date: September 20, 2010
Construction completed: October 29, 2010 (Closed 39 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route N
Bridge location: Brush Creek
Work to be done: Bridge replacement
Originally built: 1950
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 12, 2010
Construction Completed: June 1, 2010 (Closed 51 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route O
Bridge location: Indian Creek
Work to be done: Bridge replacement
Originally built: 1950
Awarded to: KTU Constructors (Design-Build Contract)
Closure date : August 16, 2010
Construction completed: September 24, 2010 (Closed 39 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route O
Bridge location: Donaby Creek
Work to be done: Bridge replacement
Originally built: 1950
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 6, 2010
Construction Completed: August 13, 2010 (Closed 38 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route F
Bridge location: Panther Creek
Work to be done: Bridge replacement
Originally built: 1951
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 22, 2010
Construction completed: October 28, 2010 (Closed 36 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route CC
Bridge location: Cat Creek
Work to be done: Bridge replacement
Originally built: 1953
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 10, 2011
Construction completed: November 4, 2011 (Closed 24 days)
Detour map: Click here for Route CC Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route Z
Bridge location: Shain Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 14, 2010
Construction completed: September 3, 2010 (Closed 51 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route M
Bridge location: West Fork Big Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 18, 2010
Construction completed: October 5, 2010 (Closed 49 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route Y
Bridge location: Trail Creek
Work to be done: Bridge replacement
Originally built: 1956
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 7, 2010
Construction completed: November 24, 2010 (Closed 47 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route AA
Bridge location: Big Creek
Work to be done: Bridge redeck
Originally built: 1962
Award amount: $353,788.00
Awarded to: Chester Bross Construction Co.
Closure date: August 30, 2010
Construction completed: October 29, 2010 (Closed 60 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route B
Bridge location: BR
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 7, 2010
Construction completed: July 12, 2010 (Closed 36 days)
|
|
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route B
Bridge location: Panther Creek
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure Date : July 19, 2010
Construction completed: August 25, 2010 (Closed 38 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route B
Bridge location: Drainage Ditch
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 25, 2010
Construction completed: June 23, 2010 (Closed 30 days) |
| |
|
|
 |
|
Route: MO 46
Bridge location: West Fork Big Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract)
Scheduled for construction: June 25, 2012
Detour map: Click here for MO 46 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 46
Bridge location: East Fork Big Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 1, 2010
Construction completed: July 23, 2010 (Closed 53 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 46
Bridge location: Shain Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 22, 2010
Construction completed: May 14, 2010 (Closed 54 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route A
Bridge location: Big Panther Creek
Work to be done: Bridge replacement
Originally built: 1949
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 5, 2010
Construction completed: May 18, 2010 (Closed 44 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 59 Hwy.
Bridge location: Little Tarkio Creek
Work to be done: Bridge replacement
Originally built: 1926
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: August 22 , 2011
Construction completed: October 11, 2011 (Closed 49 days)
Detour map: Click here for US 59 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After
PROJECT COMPLETE
 
Before After
|
|
Route: Route B
Bridge location: Nichols Creek (South)
Work to be done: Bridge replacement
Originally built: 1953
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 4, 2011
Construction completed: May 9, 2011 (Closed 35 days)
Detour map: Click here for Route B Detour
Route: Route B
Bridge location: Nichols Creek (North)
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 9, 2011
Construction completed: June 29, 2011 (Closed 51 days)
Detour map: Click here for Route B Detour
|
PROJECT COMPLETE
 
Before After |
|
Route: Route B
Bridge location: Lincoln Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: June 27, 2011
Construction completed: August 24, 2011 (Closed 55 days)
Detour map: Click here for Route B Detour |
PROJECT COMPLETE

Before |
|
Route: MO 111
Bridge location: Old Channel of Big Tarkio
Work to be done: Bridge replacement
Originally built: 1956
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: April 16, 2012
Construction completed: May 21, 2012 (Closed 37 days)
Detour map: Click here for MO 111 Detour
|
| |
|
|
PROJECT COMPLETE

Before |
|
Route: MO 111
Bridge location: Cannon Creek
Work to be done: Bridge replacement
Originally built: 1956
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: March 5, 2012
Construction completed: April 4, 2012 (Closed 30 days)
Detour map: Click here for MO 111 Detour |
| |
|
|
PROJECT COMPLETE

Before |
|
Route: Route C
Bridge location: Mid Branch of Squaw Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: March 19, 2012
Construction completed: May 1, 2012 (Closed 43 days)
Detour map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Squaw Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 3, 2011
Construction completed: November 1, 2011 (Closed 28 days)
Detour map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route N
Bridge location: East Branch of Squaw Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 21, 2011
Construction completed: May 27, 2011 (Closed 67 days)
Detour map: Click here for Route N Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route N
Bridge location: Mid Branch of Squaw Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 26, 2011
Construction completed: July 18, 2011 (Closed 53 days)
Detour map: Click here for Route N Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: MO 111
Bridge location: Corn Creek
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 11, 2011
Construction completed: May 26, 2011 (Closed 45 days)
Detour map: Click here for MO 111 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Wildcat Creek
Work to be done: Bridge replacement
Originally built: 1949
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: September 6, 2011
Construction completed: October 5, 2011 (Closed 29 days)
Detour map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route C
Bridge location: Minnesota Valley Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 18, 2011
Construction completed: September 2, 2011 (Closed 45 days)
Detour map: Click here for Route C Detour |
PROJECT COMPLETE
 
Before After
|
|
Route: DD
Bridge location: Parsons Creek
Work to be done: Bridge replacement
Originally built: 1951
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 27, 2010
Construction completed: October 29, 2010 (Closed 35 days) |
PROJECT COMPLETE
 
Before After
|
|
Route: E
Bridge location: Big Muddy Creek
Work to be done: Bridge replacement
Originally built: 1952
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 7, 2010
Construction completed: Noveber 11, 2010 (Closed 44 days) |
PROJECT COMPLETE
 
Before After |
Route: D
Bridge location: Old Channel Shoal Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 28, 2010
Construction completed: September 10, 2010 (Closed 43 days) |
PROJECT COMPLETE
 
Before After |
Route: K
Bridge location: Old Medicine Creek Channel
Work to be done: Bridge replacement
Originally built: 1938
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 27, 2010
Construction completed: September 13, 2010 (Closed 33 days) |
| |
|
PROJECT COMPLETE
 
Before After |
|
Route: P
Bridge location: Big Branch
Work to be done: Bridge replacement
Originally built: 1952
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 18, 2010
Construction completed: November 12, 2010 (Closed 45 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 136 Hwy.
Bridge location: Wildcat Creek
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: October 3, 2011 Construction completed: November 17, 2011 (Closed 43 days) Detour map: Click here for U.S. 136 Hwy. Detour
|
| |
|
|
 |
|
Route: U.S. 71 Hwy.
Bridge location: White Cloud Branch
Work to be done: Bridge replacement
Originally built: 1933
Awarded to: KTU Constructors (Design-Build Contract)
Scheduled for construction: May 29, 2012
Detour map: Click here for U.S. Hwy. 71 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route J
Bridge location: Sleek Creek
Work to be done: Bridge replacement
Originally built: 1939
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 27, 2010
Construction completed: November 2, 2010 (Closed 36 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 246
Bridge location: Honey Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 28, 2011
Construction completed: June 17, 2011 (Closed 81 days)
Detour map: Click here for MO 246 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 246
Bridge location: Brushy Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 1, 2011
Construction completed: September 2, 2011 (Closed 32 days)
Detour map: Click here for MO 246 Detour |
| |
|
|

|
|
Route: Route A
Bridge location: Elkhorn Creek
Work to be done: Bridge redeck
Originally built: 1953
Scheduled for construction: June 5,2012
Detour map: Click here for Route A Detour |
| PROJECT COMPLETE |
|
|
 
Before After |
|
Route: Route JJ
Bridge location: West Fork 102 River
Work to be done: Bridge redeck
Originally built: 1955
Awarded on: March 4th
Award Amount: $314,107.11
Awarded to: A.M. Cohron & Sons, Inc.
Closure date: July 27, 2009
Completion date: September 14, 2009 (Closed 48 days) |
| |
|
|
NOW CLOSED

|
|
Route: Route VV
Bridge location: Long Branch
Work to be done: Bridge redeck
Originally built: 1956
Closed for construction: May 14, 2012 (Six to eight week closure)
Detour map: Click here for Route VV Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 246
Bridge location: Norvey Creek
Work to be done: Bridge replacement
Originally built: 1952
Awarded to: KTU Constructors (Design-Build Contract)
Closed date: March 14, 2011
Completion date: April 29, 2011 (Closed 47 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route NN
Bridge location: Honey Creek
Work done: Bridge redeck
Originally built: 1955
Award amount: $238,560.34
Awarded to: Loch Sand and Construction Co.
Closure date: March 17, 2009
Construction completed: April 29, 2009 (Closed 43 Days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route NN
Bridge location: Brushy Creek
Work to be done: Bridge redeck
Originally built: 1955
Award amount: $194,738.84
Awarded to: Loch Sand and Construction Co.
Closure date: April 1, 2009
Construction completed: May 12, 2009 (Closed 42 Days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route PP
Bridge location: Huff Creek
Work to be done: Bridge redeck
Originally built: 1961
Awarded on: September 2, 2009
Award amount: $255,609.75
Awarded to: Boone Construction Co.
Closure date: October 13, 2009 Construction completed: November 17, 2009 (Closed 35 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route PP
Bridge location: Maupin Creek
Work to be done: Bridge redeck
Originally built: 1961
Awarded on: September 2, 2009
Award amount: $259,039.75
Awarded to: Boone Construction Co.
Closure date: March 8, 2010 Construction completed: April 12, 2010 (Closed 37 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route A
Bridge location: Jenkins Creek
Work to be done: Bridge replacement
Originally built: 1930
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: February 28, 2011
Construction completed: April 22, 2011 (Closed 53 days)
Detour map: Click here for Route A Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 113
Bridge location: Nodaway River
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: July 5, 2011
Construction completed: September 22, 2011 (Closed 77 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: MO 113
Bridge location: Nodaway River South Overflow
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 10, 2011
Construction completed: July 5, 2011 (Closed 56 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 113
Bridge location: Nodaway River North Overflow
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: March 21, 2011
Construction completed: May 10, 2011 (Closed 49 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 113
Bridge location: Cayhoga Creek
Work to be done: Bridge replacement
Originally built: 1950
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: June 2, 2011
Construction completed: July 1, 2011 (Closed 28 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 113
Bridge location: Bowman Branch
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: July 6, 2011
Construction completed: August 8, 2011 (Closed 32 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE

Before |
|
Route: MO 113
Bridge location: Sand Creek
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: April 2, 2012
Construction completed: May 7, 2012 (Closed 36 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route F
Bridge location: Mozingo Creek
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 30, 2010
Construction completed: October 5, 2010 (Closed 35 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Shankton Branch
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 20, 2010
Construction completed: October 23, 2010 (Closed 42 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: Route 139
Bridge location: Barber Creek
Work to be done: Bridge replacement
Originally built: 1933
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 19, 2010
Construction completed: October 2, 2010 (Closed 45 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route EE
Bridge location: West Locust Creek
Work to be done: Bridge deck replacement
Originally built: 1960
Closure date: March 8, 2010
Construction completed: April 21, 2010 (Closed 44 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 136
Bridge location: East Locust Creek
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 2, 2010
Construction completed: September 23, 2010 (Closed 56 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 5
Bridge location: Blackbird Creek
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 9 , 2010
Construction completed: July 23, 2010 (Closed 42 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 139
Bridge location: Unnamed Stream
Work to be done: Bridge replacement
Originally built: 1933
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: November 3, 2010
Construction completed: November 30, 2010 (Closed 35 days) |
PROJECT COMPLETE
 
Before After
|
|
Route: Route 6
Bridge location: Muddy Creek
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 18, 2010
Construction completed: November 23, 2010 (Closed 31 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 5
Bridge location: Elmwood Creek
Work to be done: Bridge replacement
Originally built: 1929
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 29, 2010
Construction completed: October 27, 2010 (Closed 31 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 129
Bridge location: Little Yellow Creek
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 29, 2010
Construction completed: November 2, 2010 (Closed 36 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Little Yellow Creek
Work to be done: Bridge replacement
Originally built: 1952
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 6, 2011
Construction completed: July 12, 2011 (Closed 35 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: Route O
Bridge location: Long Branch
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 11, 2010
Construction completed: December 4, 2010 (Closed 42 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route H
Bridge location: Mussel Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 11, 2011
Construction completed: August 29, 2011 (Closed 48 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: Route N
Bridge location: Yellow Creek
Work to be done: Bridge replacement
Originally built: 1923
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 24, 2010
Construction completed: July 10, 2010 (Closed 47 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route PP
Bridge location: Middle Fork Grand River
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 1, 2011
Construction completed: September 23, 2011 (Closed 52 days)
Detour map: Click here for Route PP Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Little Rock Creek
Work to be done: Bridge replacement
Originally built: 1951
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 19, 2011
Construction completed: November 1, 2011 (Closed 42 days)
Detour map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route W
Bridge location: Bear Creek
Work to be done: Bridge replacement
Originally built: 1937
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 21, 2011
Construction completed: April 27, 2011 (Closed 37 days)
Detour map: Click here for Route W Detour |
| |
|
|
 |
|
Route: Route T
Bridge location: Lotts Creek
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Scheduled for construction: July 9, 2012
Detour map: Click here for Route T Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route W
Bridge location: Oxcart Creek
Work to be done: Bridge replacement
Originally built: 1948
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 27, 2011
Construction completed: June 6, 2011 Detour map: Click here for Route W Detour |
|
| |
| |
| |
`
|
 |
 |
 |
 |
|
 |
 |