The US 61/Route U Interchange project was a partnership between MoDOT and Crossroads Center. It is located in the southern part of Moscow Mills, south of Troy and north of Wentzville.
PROJECT: Construct a new interchange between Route U and Mette Road on US 61.
CONTRACTOR: Iron Mountain Trap Rock Company of Iron Mountain, Missouri
COST: Award is for $8,374,042.13 and does not include the cost of land provided by Crossroads Center.
TIMELINE: Utility work began in March 2009; opened to traffic August 19, 2010.
CONTACT: Christopher Knapp, P.E., Transportation Project Manager, 573-248-2579 or customer service 1-888-275-6636