Highway Construction Projects in NE Missouri (District 3)
Spring/Summer/Fall 2010
Route 54 – Install edgeline rumble strips from Mexico to Callaway County line, moving operation - COMPLETED
Route W – Economic Recovery Project - Resurfacing from Route V in Vandalia to Route K east junction, approx. 7 miles - COMPLETED
Route P - Chip seal operation from Route 154 to Route 54 at Vandalia - COMPLETED
Route KK - Chip seal operation from from Route 54 to Route J at Laddonia - COMPLETED
Route U - Chip seal operation from Route A to Route19 - COMPLETED
Route D - Chip seal operation from Route 54 to Route M - COMPLETED
Route FF - Chip seal operation from Route Z in Callaway County to Mexico City Limits - COMPLETED
Route C – Safe and Sound Bridge Project - Bridge rehabilitation and deck replacement over BNSF Railroad - COMPLETED
Route NN - Safe and Sound Bridge Project - Bridge rehabilitation and deck replacement t over Fox River near Revere - COMPLETED
Knox County
Route C – Economic Recovery Project - Resurfacing near LaGrange from Route 6 in Ewing to Route 61 near LaGrange - COMPLETED
Route K – Economic Recovery Project - Resurfacing near LaBelle from Route E to Route 6 in LaBelle, 8.2 miles - COMPLETED
Bus. Route 61 – Economic Recovery Project - Resurfacing in LaGrange from Route 61 to Route B in LaGrange, 1.8 miles - COMPLETED
Interchange at US 61/Route U in Moscow Mills - COMPLETED
Route E – Economic Recovery Project-Resurfacing near Silex from Route O North junction to Route UU in Silex, 10.9 miles - COMPLETED
Route UU – Economic Recovery Project-Resurfacing near Silex from Route Z to Route E in Silex, 4.5 miles- COMPLETED
Route U - Chip seal operation from Route J south of Troy to Route 61 - COMPLETED
Route 24/61 – Economic Recovery Project - Project includes rehabilitating both north and southbound bridges just north of Route 6 near the Taylor interchange approximately 0.9 mile north of Route 6 - COMPLETED
Business Route 61 – Resurfacing in Palmyra, 2.8 miles from just north of Route BB to just north of Routes 24 and 61 - COMPLETED
Route C – Resurfacing near Palmyra approximately 9.8 miles from Route Z west junction to Route 168 - COMPLETED
Route 24 – Safe and Sound Bridge Project - Bridge Rehabilitation on northbound North River Bridge just north of Palmyra - COMPLETED
Business Route 61 overpass – Safe and Sound Bridge Project - Bridge deck replacement and painting steel girders on overpass over Routes 61/24 at south end of Palmyra - COMPLETED
Interstate 72 – Resurfacing at I-72/US 36 interchange in Hannibal - COMPLETED
Route 36 Marion/Shelby – Rehabilitating pavement on eastbound lanes from 1.6 miles west of Route Z at Hunnewell in Shelby County to 0.7 mile west of Business 36 west junction at Monroe City, 7.231 miles - COMPLETED
Route 24 – Installation of edgeline rumble strips from Monroe City to Madison - COMPLETED
Route 151– Rehabilitate bridge over Elk Fork Salt River near Madison with epoxy polymer concrete overlay and upgrade guardrail ends - COMPLETED
Route 19 – Economic Recovery Project-Resurfacing from Route B (just north of Montgomery City) to 1.7 miles south of Interstate 70 - COMPLETED
Route F - Chip seal operation from Route V to I-70 - COMPLETED
Route J - Chip seal operation from Route 19 to Route N in Mineola - COMPLETED
Route 61 – Resurfacing from 0.8 mile south of Route UU near Bowling Green south to just north of Route OO near Eolia (five disconnected sections) - COMPLETED
Route Y – Economic Recovery Project - Resurfacing near Bowling Green from Business Route 61 in Bowling Green to County Road 486, 2.4 miles - COMPLETED
Route 79 - Rehabilitate bridge over Sugar Creek near Ashburn with epoxy polymer concrete overlay and upgrade guardrail ends - COMPLETED
Routes W - Chip seal operation from Paynesville to Clarksville - COMPLETED
Route WW - Chip seal operation from between D & W - COMPLETED
Route D - Chip seal operation from Louisiana to Eolia - Route 79 to 61 - COMPLETED
Route ZZ - Resurface near Frankford from Route 61 to the end of state maintenance - COMPLETED
Route M - Chip seal operation from Route 61 west to the end of State Maintenance - COMPLETED
Route H -Chip seal operation from Route 19 at Center north to Route 36 - COMPLETED
Route A - resurface Route A south of Monroe City from Route J east to Route H - COMPLETED
Route D - Safe and Sound Bridge Project - Bridge rehabilitation and deck replacement over North Fork of Middle Fabius River Bridge southwest of Memphis - COMPLETED
US Route 36 - Construction to add lanes for four-lane highway between Macon and Monroe City - 52 miles. Four lane open to Shelbina with construction in progress on section between Shelbina and Clarence - COMPLETED
Route 36 Shelby/Marion – 0% complete - Project involves rehabilitating pavement on eastbound lanes from just east of the Macon County line to just west of Business 36 west junction at Monroe City (4 disconnected sections)*, approximately 20.127 miles. Traffic will be reduced to one lane traffic with 45 mph speed limit through the work zone. - IN PROGRESS THRU SUMMER 2011
Interstate 70 - Installing edgeline rumble strips from St. Charles to Montgomery County line - COMPLETED
Route B – Economic Recovery Project - Intersection and outer road improvements 0.2 mile south of Interstate 70 near the Flying J - COMPLETED