Safe & Sound will repair or refurbish 13 bridges in 2012.

For more information on the Safe & Sound Bridge Improvement Program, review the project website. Also review the Safe & Sound press room for downloadable photos, press releases, fact sheets and maps.

divider

Route: Route 7 at Camp Creek

Bridge No.:  G0986

Construction Start: Winter 2012

Days closed: TBA

Contractor:

Detour: Route P

Status:

Daily traffic volume: 5,150


Route:  Route B at Grand River

Bridge No.:  T0502

Construction Start: Winter 2012

Days closed: 49 days

Contractor: KTU Constructors

Detour: Route T

Status:

Daily traffic volume: 936


Route:  Route Y at Massey Creek

Bridge No.: W0122

Construction Start: Winter 2012

Days closed: 35

Contractor: KTU Constructors

Detour: Route C

Status:

Daily traffic volume: 742


Route:  Route N at Walnut Creek

Bridge No.:  Y0947

Construction Start: Spring 2012

Days closed: 39

Contractor: KTU Constructors

Detour: Routes Z and ZZ

Status:

Daily traffic volume: 521


Route: Route E at Crawford Creek

Bridge No.:  P0550

Construction Start: Spring 2012

Days closed: 49

Contractor: KTU Constructors

Detour: Routes 58 and VV

Status:

Daily traffic volume: 720


 

clay

Route: Route 92 at First Creek    

Bridge No.:  J0923

Construction Start: February 14

Days closed: Through end of April 

Contractor: Widel Inc.

Detour: Route 169, I-435 and Route C

Status:

Daily traffic volume: 4400


Route: Route 69 at BNSF Railroad

Bridge No.:  K0140

Construction Start: Spring 2012

Days closed: 38

Contractor: KTU Constructors

Detour: A bypass will be built to allow traffic to move around closure

Status:

Daily traffic volume: 11181


Route: Route 69 at BNSF Railroad

Bridge No.:  L0502

Construction Start: Spring 2012

Days closed: 29

Contractor: KTU Constructors

Detour: A bypass will be built to allow traffic to move around closure

Status:

Daily traffic volume: 11181


Route: Route 69 South at Branch Williams Creek

Bridge No.:  J0331

Construction Start: Winter 2012

Days closed: TBD

Contractor:

Detour: Routes 92 and PP

Status:

Daily traffic volume: 6659

   
johnson county

Route: Route 2 at Bear Creek

Bridge No.:  T0852

Construction Start: March 5, 2012

Days closed: Expected to reopen by end of April

Contractor: KTU Constructors

Detour: Routes N and B

Status:

Daily traffic volume: 560


Route: Route 58 at Union Pacific Railroad

Bridge No.:  K0429

Construction Start: Summer 2012

Days closed: 53

Contractor: KTU Constructors

Detour: Routes 50 and 131

Status:

Daily traffic volume: 2643


Route: Route B at Walnut Creek

Bridge No.:  N0429

Construction Start: April 30, 2012

Days closed: Expected to reopen by mid June.

Contractor: KTU Constructors

Detour: Routes N and B

Status:

Daily traffic volume: 703


saline

Route: Route 127 at Kansas City Southern Railroad

Bridge No.:  L0392

Construction Start: Spring 2012

Days closed: 75

Contractor: TBD

Detour: Route BB

Status:

Daily traffic volume: 246


   
   
   